Use this checklist to aid in commissioning a new SiteWorx facility. If you're unfamiliar with Commissioner and Mapfiles, we suggest reviewing this Overview article first.
Want to expedite commissioning? Contact sales@siteworx.io about purchasing factory onsite or remote commissioning services.
Latest 2D lighting layout or floorplan, in PDF or JPEG format
Site-required Personal Protective Equipment
Light meter
Recommended Items
Manlift
micro-USB cable
2x 10' ethernet cables
RJ45 termination kit
Commissioning Checklist
Before the Visit
Verify installation is complete
Verify the Sticker Map is complete and will be available onsite during the commissioning visit
Verify gateways are connected and online (contact support@siteworx.io to verify; Certified Resellers can use the online connectivity tool)
Speak to the end-user about naming conventions - building name(s), work area names, aisle names, etc. and make detailed notes on the floorplan
If possible, request a clean work surface at the site - preferably a conference room with a large, open table
Speak to the SiteWorx Admin to make sure they've successfully logged in to SiteWorx for the first time
If possible, request that they approve an account for your use during installation, noting that it can be deleted afterwards. Follow the Create an Account procedure
Create a Mapfile for each building and/or floor of a building at the site
Save often We recommend using the following filename structure: YYYYMMDD HHMM OrgName - AreaName - [summary of changes].map
Add facility details (Map > Site Configuration)
Complete the General section and the Date/Time Settings section
Email the .map mapfile(s) to siteworxops@siteworx.io for upload. Please include the Subscription Number (SUB-XXXXX) Note: This step activates the subscription term, and will initiate billing within 24hrs
Once live, and assuming the Admin approved your access:
Ensure all names are correct (Org, Site, Area, Groups, Devices)